Karon Heights Residence, Phuket Property, Thailand

Progress of work

 

May 2010

 

  • 1 May 2010
    • Club House
    • Roof Completed.
    • Ceiling is 90% completed.

  • 2 May 2010
    • Classrooms Building
    • Roof is completed.
    • 80% of the outer wall is completed.
    • 60% of the ceiling structure is completed.
  • 2 May 2010
    • Gymnasium
    • 85% of the outer wall is completed.
    • Metal sheet on the roof is completed.
  • 3 May 2010
    • Dormitory
    • Roof is completed.
    • 60% of the ceiling structure is completed.
    • 90% of the 3rd floor outer wall is completed.

 

 

June 2010

 

  • 1 June 2010
    • Club House
    • Roof Completed.
    • Ceiling is 90% completed.

  • 2 June 2010
    • Classrooms Building
    • Roof is completed.
    • 80% of the outer wall is completed.
    • 60% of the ceiling structure is completed.
  • 2 June 2010
    • Gymnasium
    • 85% of the outer wall is completed.
    • Metal sheet on the roof is completed.